A fault on the Meghnaghat–Haripur national grid line disrupted electricity supply in parts of Dhaka and Chattogram on Tuesday, affecting neighbourhoods in the capital as well as key public installations. The outage was regional, not a nationwide blackout, and the technical cause was still being investigated in the reports reviewed.
Power Grid Bangladesh PLC said the disruption began at about 12:43pm local time. Reporting by The Daily Star identified areas including Bhulta, Haripur, Siddhirganj, Gulshan, Rampura, Ullon and Motijheel, along with parts of Chattogram. The newspaper said the Secretariat was without electricity for nearly an hour.
The incident was also felt at Bangladesh Bank and courts, according to New Age. Its report said the disruption affected households, businesses and key installations while the state grid operator brought the system back. Reports did not establish a customer total, so this article does not infer one.
The disruption was serious without being nationwide. The Daily Star said northern Bangladesh and other unaffected areas remained normally supplied. That distinction matters because the event involved a line fault and a sharp loss of available generation, not a confirmed collapse of the whole national electricity system. It also explains why separate reports can accurately describe both a completed grid restoration and continued localised load-shedding while plants returned to service.
New Age reported that National Load Dispatch Centre supply fell from 14,303MW at 11:00am to 8,899MW at 1:00pm. It also said some smaller gas-fired units tripped during the disturbance and that steam-turbine units could take longer to resume. The reports support a phased return of supply, not a single all-clear moment for every location.
The immediate effect on the power system was substantial. The Business Standard reported that national generation fell by 5,370MW in about an hour, from 14,719MW at noon to 9,349MW at 1pm. It said gas-fired generation experienced the largest fall, while grid and power-sector teams worked to reconnect plants and stabilise supply.
By mid-afternoon, Power Grid Bangladesh said restoration work on the national grid had been completed. The Financial Express reported that all grid transmission lines and substations had returned to service at 2:30pm. That milestone should not be read as proof that every local supply issue ended at the same moment. Power plants were being restarted in phases, and the utility said any localised load-shedding associated with reduced generation should ease as output increased.
The reports converge on the location and timing of the fault, but they do not provide a final technical explanation. Officials described a fault involving the Meghnaghat–Haripur line, and the Financial Express reported that Power Grid Bangladesh formed a five-member committee to investigate. Until its findings are public, it would be premature to assign the event to a specific equipment failure or operational error.
For organisations that depend on stable electricity and communications, an event like this is also a reminder to separate a grid-level recovery update from an application or website’s actual availability. Teams can follow the electricity and gas service category and the Bangladesh Power Development Board service page on Status Is Down, while keeping their own status communications ready for customers and staff.
Outage response is clearer when monitoring, escalation and public updates are planned before the next disruption. Explore Status Is Down plans for monitoring tools designed to help teams notice availability issues and communicate with confidence.
This report is based on independently published newsroom coverage and operator-attributed updates. It reports the disruption and restoration steps described above; it does not claim a confirmed root cause, nationwide scope, or a verified customer-level completion time.